Commissioning on cards as QCLNG moves towards first gas

UNDERTAKING the first LNG tank test on Curtis Island and commissioning gas turbine generators are on the cards for QGC this year.

QGC is partnering with BG Group to build the QCLNG project on Curtis Island.

In an interview with the Queensland Mining and Energy Bulletin, QGC managing director Derek Fisher said the first LNG tank hydro-test would be carried out in the first quarter.

Gas turbine generators will be commissioned in the second quarter, followed by the commissioning of Train 1.

This will lead to the first commercial cargo in the fourth quarter, and Train 2 about six months later.

Mr Fisher said one of QGC's greatest achievements had been its ongoing relationships with communities from Gladstone to the Surat Basin.

You can read the full interview here.



'We are frightened': Woman slams govt for lack of support

'We are frightened': Woman slams govt for lack of support

A Nimbin woman has interrupted a press conference with Labor leader

36 bison at tourist park ready for onslaught of fire

premium_icon 36 bison at tourist park ready for onslaught of fire

We have a fire pump and 20,000-litre tank and sprinkler system.

Aboriginal graves threatened by 175-lot river development

premium_icon Aboriginal graves threatened by 175-lot river development

Bandjalang woman Simone Roberts opposes coastal development